224-0239/01 – Excavation and Supporting of Underground Constructions (RVPHD)
Gurantor department | Department of Geotechnics and Underground Engineering | Credits | 4 |
Subject guarantor | Ing. Lukáš Ďuriš, Ph.D. | Subject version guarantor | Ing. Lukáš Ďuriš, Ph.D. |
Study level | undergraduate or graduate | Requirement | Compulsory |
Year | 3 | Semester | summer |
| | Study language | Czech |
Year of introduction | 2014/2015 | Year of cancellation | |
Intended for the faculties | FAST | Intended for study types | Bachelor |
Subject aims expressed by acquired skills and competences
The aim of the course is to introduce students with the technology of underground excavation works
particularly small cross dimensions (collectors, galleries, water and sewer facilities, gallery and gallery), focusing on drilling and blasting work. Part of the design and dimensions support construction, machinery and determine the face of technological times excavation cycle of operations. Next is devoted to continuous excavation technology by tunnelig machines, TBM.
Teaching methods
Lectures
Tutorials
Summary
The main topic of the course is to get acquainted with the problems of underground support structures and their construction technology. There are defined basic requirements for the design of underground and mine workings. The reinforcements are divided according to individual materials and their flatness. The parameters of bolts and bolt reinforcement are defined here. The subject also solves the technology of the construction of horizontal linear works (galleries) by the conventional method of excavation. The individual stamping operations and the machinery used in the excavation are analyzed. Part of the subject is an introduction to the continental method of stamping underground works.
Compulsory literature:
Recommended literature:
Way of continuous check of knowledge in the course of semester
E-learning
Other requirements
Completion of the course blasting.
At least 70% attendance at the exercises. Absence, up to a maximum of 30%, must be excused and the apology must be accepted by the teacher (the teacher decides to recognize the reason for the excuse).
Tasks assigned on the exercises must be hand in within the dates set by the teacher.
Prerequisities
Subject has no prerequisities.
Co-requisities
Subject has no co-requisities.
Subject syllabus:
Lectures topic:
- Underground work, its functions and basic parameters - the shape of a cross-section.
- Rock mass classification and marking of underground workings.
- Reinforcing materials and construction.
- rock bolting, anchoring
- Stability of mine workings and the calculation of support construction work.
- The basic distribution methods for stamping ground works and the selection of optimal methods.
- Major and minor operations tunneling cycle classical kind.
- Organization of work during the excavation, the use of computer technology, technical stamping documents.
- Striking the anomalous conditions.
- Striking inclined underground workings.
- Striking penetrates underground - turning, cross work.
- Striking spacious underground mines and construction of large sections.
- The basic criteria for mechanical rock underground.
- Excavation beam tunnel boring machine - roadheaders.
- Excavation TBM tunneling (boring machine and shields).
Exercise topic:
Design parameters of a wooden frame reinforcement of the underground work (a small cross section, small depth below the surface).
Design parameters of flat ground for concrete reinforcement work of round section
mined in great depth.
Comprehensive design classic technology for underground excavation works less cross section (<16 m2):
- Design and calculation of the support construction (steel frame reinforcement)
- Technological process of blasting
- Mechanical equipment design and calculation time of the main technological operations excavation cycle (drilling, blasting, Removal of muck, reinforcing)
- Auxiliary Operations tunneling cycle (separate ventilation, water, air, equipment)
The complex process of technological design for classic excavation underground structure with cross section 16 m2:
Design and calculation of the support construction (anchoring)
- Technological process of blasting
- Mechanical equipment design and calculation time of the main technological operations excavation cycle (drilling, blasting, Removal of muck, reinforcing)
- Auxiliary Operations tunneling cycle (separate ventilation, water, air, equipment)